This Week – 5/27 to 6/3

  • Finished installing Water Line on Virginia and tested
  • Fiinishing up the Duct Bank on Appling Way

    Next Week – 6/3 to 6/10
  • finish Chlorination of water line Virginia Place
  • Begin installing sewer on Virginia
  • Finish working on Appling Way Duct Bank and demobilize
  • PNG/SEC mobilize and begin installing gas line on Appling
  1. 7/28/20
  2. 8/6/20
  3. 8/19
  4. 8/26

This Week – 7/22 to 7/29

  • Worked on Curb and asphalt on Appling Way
  • Staked for retaining wall
  • Finished Virginia Place

 Next Week – 7/29 to 8/5

  • Continue curb and asphalt on Appling Way
  • Start building the retaining wall
  • Begin demo of Pine Street (Pine Street Elevations Needed)
  1. 9/2/20
  2. 9/17/20

This Week – 8/26 to 9/2

  • Continued demo of Pine Street
  • Continued sidewalk on Appling Way
  • Installed Fence at retaining wall
  • Continued curb on Appling Way around curve tying into Pine
  • Installed Asphalt around curve on Appling way tying into Pine

 

Next Week – 9/2 to 9/9

  • Continue demo of Pine Street
  • Continue sidewalk on Appling Way
  • Continue paving